How Modular Changes the Construction Draw Schedule

Most construction lenders know the stick-built draw schedule. Land closing, site work, foundation, framing, rough MEP, drywall, finishes, CO. Each draw corresponds to an inspection milestone. The lender inspector visits the site, confirms progress, and releases funds.

A modular project does not work this way.

![Construction pro forma analysis on laptop](https://yyjfntvzblexehejwjbm.supabase.co/storage/v1/object/public/blog-images/pro-forma-analysis.jpg)

Factory Draws Need Different Triggers

In volumetric modular, a significant portion of construction cost is incurred at the factory before any site work begins. Factory purchase agreements typically require 10% to 20% at execution, 20% to 30% at production start, 20% to 30% at module completion, and the balance at delivery.

On a project where modules represent 50% to 60% of hard costs, you may need to fund 40% to 50% of your factory contract before you have anything to show an on-site inspector.

> Zero percent on site one week, 80% three weeks later is normal and expected. Pre-educate your lender inspector.

The lender inspector is accustomed to visiting a site and seeing incremental progress. On a modular project, the site may show only foundation work for months while the factory is producing modules. Then within a matter of days, fully finished units appear on-site. This visual disconnect creates lender anxiety that can be managed with proper communication upfront.

Some lenders now accept factory inspection reports as draw triggers. A qualified third-party inspector visits the factory, confirms production milestones, and issues a report that supports the draw request. This approach aligns the draw schedule with actual progress rather than on-site visibility.

Retainage

Factories will not accept standard 10% retainage. Negotiate 2% to 5% maximum, held 30 to 60 days post-delivery, separately from site contract retainage. Attempting to impose standard retainage terms on a factory will either kill the deal or result in inflated pricing to compensate for the cash flow impact.

Have This Conversation Early

Walk your lender through the factory draw schedule before loan closing. Confirm they can fund factory draws before on-site progress is visible. Get inspection triggers written into the loan agreement that reference factory milestones, not just site milestones.

Six months of schedule compression on a $4,000,000 construction loan at 8% equals $160,000 in interest saved. That belongs in your pro forma from day one, and your lender needs to understand why the draw schedule looks different from what they are used to seeing.